UPDATE
BUILDING WORK HAS BEGUN!
WEEKS COMPLETED:
WEEK 1 (11.03.19 - 17.03.19)
Initial setup
WEEK 2 (18.03.19 - 24.03.19)
Stripping down and ground floor foundation pits
WEEK 3 (25.03.19 - 31.03.19)
Ground floor foundation pits and further stripping down of ceiling
WEEK 4 (01.04.19 - 07.04.19)
Removal of electrics, wiring and ceiling
WEEK 5 (08.04.19 - 14.04.19)
New ground floor flooring and filling in of foundation holes/pits with concrete
WEEK 6 (15.04.19 - 21.04.19)
Further exploration work and completion of flooring
WEEK 7 & 8 (22.04.19 - 05.05.19)
No work completed during this period as a number of issues with the floor although many planning meetings took place
WEEK 9 (06.05.19)
Complete removal of all joists on the first floor and further stripping out
Week 10 (13.05.19 - 19.05.19)
Steel preparation, painting and installation of new joists
Week 11 ( 20.05.19 - 26.05.19)
New flooring installation over new joists and formation of new fire exit platform. Also basic installation of new staircase.
Week 12 ( 27.05.19 - 02.06.19)
Completion of internal staircase, existing external fire exit door removed and filled in, new fire exit door in external wall opened up, 87 % completion of the 1st floor flooring, and electrical wiring.
Week 13 (03.06.19 - 09.06.19)
New partition built that separates the nursery to the building site area. Completion of the rest of 1st floor flooring and installation of new electrical box. Formation of 1st floor fire exit staircase area and three steps located at new first floor fire exit door.
Week 14 (10.06.19 - 16.06.19)
Preparation of wood work and doors that will be installed after partition work has been completed on ground floor and 1st floor. Delivery of glass and other building components. 1st floor partition erected to make a new corridor around the lift shaft.
Week 15 (17.06.19 - 23.06.19)
1st floor partition roof installed and windows cut out, new double door positioned, and numerous partition panels placed. Electrical wiring and installation of the smoke/heat sensors, emergency lighting and main lighting.
Week 16 (24.06.19 - 30.06.19)
Partitioning of the beams/metal work that go across the ceiling of the ground floor. Partition of the internal staircase and new partition on ground floor to make ground floor corridor.
Week 17 (01.07.19 - 07.07.19)
The rear fire exit area was excavated, the astro-turf in the rear garden was taken up and fencing erected to protect the children's play area. Ground floor partition and ground floor and 1st floor electrical wiring of the main lights and some floor boxes.
Week 18 (08.07.19 - 14.07.19)
The rear fire exit foundation pit was dug and lift pit work was completed to raise to the required level. This was filled with cement.
Week 19 (15.07.19 - 21.07.19)
All glass work completed and ground floor double doors hanged. Rear fire escape delivered and secured in location.
PICTURES